See what a change-notice draft can look like.

This text-only sample shows the five sections used to organize a Change Notice. Every project detail below is fictional and written for illustration.

Illustrative change-notice example

Fictional extra-work draft

Cedar Vale Clinic Build-Out

Project details · all fictional

Project number
CD-EX-104 (fictional)
Location
Spokane, Washington (fictional)
Work date
August 12, 2026 (fictional)
General contractor
Northline Build Group (fictional)
Trade subcontractor
Sampleline Mechanical (fictional)

Scope

Fictional illustration: relocate eight wall sleeves to match a revised partition layout. Confirm the described work and applicable project procedures against the project records.

Labor

Fictional illustration: Two installers at four additional hours each, for eight installer-hours total. Applicable labor rates were not supplied and need confirmation.

Materials

Fictional illustrative estimate: $480 for materials. Confirm the quantities, pricing basis, and actual material cost.

Schedule impact

Not estimated in this fictional example. Confirm any schedule effect against the current project schedule.

Authorization request

Please review the described work and confirm the applicable project procedures, labor rates, and any schedule effect. Please advise whether further authorization steps apply. This sample states no contract rights or conclusions.

Illustrative Plumbing Change Notice

Example Clinic Fit-Out (fictional project)

Every project detail and dollar amount in this example is fictional and only demonstrates how supplied information can be organized. It is not a real customer case, quote, or cost estimate.

Original job number
PL-EX-042 (fictional job number)
Affected plumbing drawing
P-2.1, Revision B, Detail 4 (fictional reference)
Affected specification
Section 22 11 16, §3.2 (fictional reference)
Recipient
Not supplied; no recipient assumed.
Plumbing contractor
Not supplied; no contractor assumed.
Property address
Not supplied; no property address assumed.
Original estimate or contract value
Not supplied; no original amount assumed.
Change date
Not supplied; no date assumed.

Change and reason

Fictional scenario: move one lavatory’s hot- and cold-water stub-outs and waste connection 18 inches north to align with a revised casework layout.

Stated reason: Fictional stated reason: the casework layout was revised, moving the sink centerline.

Category: Design revision (fictional category)

Proposed scope

Included
Fictional proposed scope: relocate the hot- and cold-water stub-outs and waste connection for one lavatory, then reconnect the branch at the revised centerline.
Excluded
Fictional proposed exclusion: casework changes and finish restoration. Confirm any other exclusions against the project records.
Access holes
Not supplied; confirm whether access holes are needed and included.
Patching
Not supplied; confirm whether patching is included or excluded.
Painting
Not supplied; confirm whether painting is included or excluded.

Illustrative cost breakdown (USD)

Fictional sample values only. Confirm actual quantities, units, rates, and amounts; no revised contract total is supplied.

Labor · fictional amount

Quantity and unit
6 plumber-hours
Unit cost
$90.00
Extended cost · fictional
$540.00

Materials · fictional amount

Quantity and unit
12 linear feet
Unit cost
$8.50
Extended cost · fictional
$102.00

Permit allowance · fictional amount

Quantity and unit
1 allowance
Unit cost
$75.00
Extended cost · fictional
$75.00

Markup · fictional amount

Quantity and unit
1 lot
Unit cost
$71.70
Extended cost · fictional
$71.70

Schedule

Status: Needs confirmation; no schedule effect is assumed. Added time: Not supplied; unestimated.

Contractor verification prompts

  • Lien-notice requirements and dates

    Which requirements apply to this project and contractor role? Which relevant dates need to be confirmed from project records and qualified sources?

  • Prevailing wage

    Does a prevailing-wage requirement apply? If so, which project source or qualified advisor can confirm the applicable classification and determination?

  • Warranty, insurance, and code

    Could the proposed change affect a warranty, insurance coverage, or code review? Confirm with the applicable project source or qualified professional.

  • Signers and authorization

    Who signed the original agreement? Are there other owners or signers to identify, and what review and authorization steps do the project records require before work starts?

This illustrative draft is not legal advice or contract interpretation, engineering or safety certification, and does not guarantee compliance. Review the sample against actual project records and confirm open questions with qualified sources before issuing any real document.